Question
The reply clearly explains why the schedule slipped, citing late deliveries from the train manufacturer and COVID-19 factory closures, though it does not address the phasing of the work through 2026 and 2027. On costs, it confirms that discussions on the Department's delay-related costs and East Midlands Railway's costs are ongoing, and it declines to give any figures on the grounds of commercial sensitivity. The reason for withholding is stated, but the asker still has no cost information and would likely need to ask again for specifics.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Transport, pursuant to the Answer of 1 September 2026 to Question 18909 on Rolling Stock, what assessment she has made of the reasons for the delay between the original expectation that all 33 Class 810 trains would be available for service by December 2022 and their phased introduction through 2026 and 2027; and what additional costs have been incurred by (a) her Department and (b) the operator as a result of that delay.
Answer
Delays from the train manufacturer have resulted in East Midlands Railway’s Hitachi Class 810 trains being delivered into passenger service over three years late, including due to the COVID-19 pandemic which closed factories for a period of time. DfT Operator, East Midlands Railway and Hitachi are working closely together to ensure the remaining Class 810 trains are delivered into passenger service, and the full East Midlands Railway intercity timetable is restored as soon as possible. Discussions regarding the costs incurred by the department and East Midlands Railway related to the delay to these trains are continuing and commercially sensitive.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What is the Department's assessment or view of the reasons for the delay between the original expectation that all 33 Class 810 trains would be available for service by December 2022 and their phased introduction through 2026 and 2027? | Addressed | Direct | The reply names the reasons for the delay, namely late deliveries from the train manufacturer and COVID-19 factory closures, which answers the question about the Department's view of why the schedule slipped, though it says nothing about the phasing through 2026 and 2027. |
| What additional costs have been incurred by the Department as a result of the delay to the introduction of the Class 810 trains? | Addressed | Direct | The reply states that discussions on the Department's delay-related costs are ongoing and declines to give a figure on the grounds that the information is commercially sensitive, which is a stated reason for withholding the requested cost figure rather than silence. |
| What additional costs have been incurred by the operator as a result of the delay to the introduction of the Class 810 trains? | Addressed | Direct | The reply expressly covers costs incurred by East Midlands Railway, saying these are under discussion and commercially sensitive, so it engages with the operator-cost item and gives a stated reason for not providing figures. |