The reply directly answers the question: it says the pilots at MOD Aberporth and Pendine found unforeseen technical constraints around energy storage that reduced the expected benefits. It names only one constraint and does not explain its technical nature or what was done about it, so a member of the public would have a clear answer but might still want more detail.
Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Defence, pursuant to the answer of 6 October 2026 to question 22838 on Military Bases: Solar Power, what were the unforeseeable technical constraints which limited the benefits.
Answer
The Photovoltaic Farms Project was originally planned for numerous sites. The initial pilots were at MOD Aberporth and MOD Pendine and these demonstrated both cost escalation and the unforeseen technical constraints around energy storage reducing benefits and further impacting the economic basis for the projects. The project’s original costs were estimated at £10.2 million however, by the time the project was cancelled estimated total costs had risen to £63million, based on costings received for Aberporth and Pendine.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What were the unforeseeable technical constraints which limited the benefits of solar power at military bases? | Addressed | Direct | Statement 3 directly states that the pilots at MOD Aberporth and Pendine revealed unforeseen technical constraints around energy storage that reduced the benefits, which is the specific answer asked for; statement 2 supplies the context of which pilots were involved. The reply names only one constraint and does not elaborate on its technical nature, so it is brief rather than exhaustive. |