Question
The reply directly answers the question, giving both figures requested: the original estimated cost of £10.2 million and the escalated estimated total of £63 million by the time the project was cancelled. Both numbers are stated plainly, with no hedging or deferral. The person who asked would have the specific information they sought and would be unlikely to need to ask again.
Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Defence, pursuant to the answer of 6 October 2026 to question 22838 on Military Bases: Solar Power, what did the cost escalate from and to.
Answer
The Photovoltaic Farms Project was originally planned for numerous sites. The initial pilots were at MOD Aberporth and MOD Pendine and these demonstrated both cost escalation and the unforeseen technical constraints around energy storage reducing benefits and further impacting the economic basis for the projects. The project’s original costs were estimated at £10.2 million however, by the time the project was cancelled estimated total costs had risen to £63million, based on costings received for Aberporth and Pendine.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What was the initial cost and the escalated cost of the solar power project on military bases, as referred to in the answer of 6 October 2026 to question 22838? | Addressed | Direct | The reply gives both requested figures: the original estimated cost of £10.2 million and the escalated estimated total of £63 million by the time the project was cancelled. |