Question

Asked by Nick Timothy Conservative to Ministry of Justice on 29 October 2026 — tabled under the Andy Burnham government

78/100 GREEN (78/100)

The reply gives a direct, specific answer to the question. It splits the £1.3 million write-off by site, with £834,851.76 at HMP Huntercombe and £428,435.88 at HMP The Verne, and names the main contractor (ISG Construction Limited) and the electricity subcontractor (Scottish and Southern Electricity Networks). The one limitation is that the write-off is not broken down by amount for each contractor, only by site, so a reader wanting contractor-level figures would need to ask for them.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Justice, with reference to the HMPPS Annual Report 2025 to 2026, if he will provide a breakdown of the £1.3 million worth of fruitless payments for utility infrastructure works supporting prison expansion where recovery was not possible following contractor insolvency, including which contractors this relates to.

Answer

Answered by Catherine McKinnell (Labour)

The £1.3 million write-off comprises £834,851.76 relating to HMP Huntercombe and £428,435.88 relating to HMP The Verne. At both sites, the main contractor was ISG Construction Limited and the subcontractor for the electricity infrastructure works was Scottish and Southern Electricity Networks.

How we got there

Question itemCoverageSpecificityRationale
Will the Secretary of State provide a breakdown of the £1.3 million in fruitless payments for utility infrastructure works supporting prison expansion, where recovery was not possible following contractor insolvency, including which contractors this relates to? Addressed Direct The reply gives the write-off split by site (£834,851.76 at HMP Huntercombe and £428,435.88 at HMP The Verne, which together account for the £1.3 million) and names the contractors involved (ISG Construction Limited as main contractor and Scottish and Southern Electricity Networks as electricity subcontractor), covering both parts of the request. It does not separately break down amounts by contractor, so the breakdown is site-level rather than contractor-level.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.