Question
The reply describes a concrete mechanism: projects must meet progression milestones to keep their connection agreements. It also states a general view that this supports faster progression of viable projects. It does not say how the penalty affects queue clearance rates, which was the specific point asked, so the question is only partly answered. The asker would likely need to follow up for that figure or assessment.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Energy Security and Net Zero, what assessment her Department has made of the potential impact of penalising non-ready infrastructure projects on electricity grid queue clearance rates under the Connections Action Plan.
Answer
The Department has taken forward reforms to the grid connections process, removing over 300GW of project capacity from the main queue that was no longer progressing or was not required to meet the system’s needs by 2035. Projects are required to meet ongoing progression milestones, such as securing planning consent, to retain their connection agreements with confirmed connection point and date. This supports a more efficient connections process and enables viable projects to progress more quickly.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What is the Department's assessment or view of the potential impact of penalising non-ready infrastructure projects on electricity grid queue clearance rates under the Connections Action Plan? | Partially Addressed | Direct | The reply names a concrete mechanism, progression milestones that projects must meet to keep their connection agreements, and states a general view that this supports a more efficient process and faster progression of viable projects. It does not assess how this penalty affects queue clearance rates specifically, so the answer is only partly responsive. |