Asked by James MacCleary Liberal Democrat to Ministry of Defence on 21 October 2026 — tabled under the Andy Burnham government

77/100 GREEN (77/100)

The reply gives concrete, committed information on both parts of the question. It describes the programme's progress: it is midway through the D2L2 phase, due to complete in 2028, long-lead items are being bought, steel will be cut on the first boat next year, and the first boat is aimed for service in the late 2030s. It also states the 2025-26 Government Major Projects Portfolio rating as amber and explains what that means at this stage, though the sentence does not name the SSN-AUKUS programme directly.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Defence, what progress he has made on the Submersible Ship Nuclear AUKUS programme in the context of the Delivery confidence assessments for Government Major Project Portfolio Defence projects.

Answer

Answered by Luke Pollard (Labour (Co-op))

The National Infrastructure and Service Transformation Authority Gate Review process is an integral part of the Assurance Framework that the Ministry of Defence has in place to support project delivery. The 2025-26 Government Major Project Portfolio amber assessment reflects the likelihood of successful delivery at a specific point in time and should be expected for a programme at this stage of maturity. We are making good progress in addressing the report’s findings. The programme is currently midway through the Detailed Design and Long Lead (D2L2) phase which is due to complete in 2028. This will mature the design and manufacturing arrangements, develop detailed schedules and see the purchase of key long lead items for the early boats in Class. On current plans, we will cut steel on the first SSN-AUKUS submarine next year, with the aim to deliver the first UK submarine into service from the late 2030s.

How we got there

Question itemCoverageSpecificityRationale
What progress the Secretary of State has made on the Submersible Ship Nuclear (SSN-AUKUS) programme Addressed Direct The reply describes concrete programme progress: the programme is midway through the D2L2 phase due to complete in 2028, long-lead items are being purchased, steel will be cut on the first boat next year, and the first boat is aimed for service in the late 2030s.
What the current Delivery Confidence Assessment rating is for the SSN-AUKUS programme within the Government Major Projects Portfolio Defence projects Addressed Direct The reply states the 2025-26 Government Major Projects Portfolio assessment is amber and explains what that rating means for a programme at this stage, which answers the request for the current DCA rating, though it does not name SSN-AUKUS explicitly in that sentence.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.