Question

Asked by Priti Patel Conservative to Department for Energy Security and Net Zero on 11 November 2026 — tabled under the Andy Burnham government

92/100 GREEN (92/100)

The reply directly answers the one point the question asked. It confirms that the Secretary of State has received the examining authority's report, which the Planning Inspectorate delivered on 10 November 2026, and it also gives the deadline for a decision. The answer is specific and committed, so the person who asked would be unlikely to need to ask again.

Scored 19 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, whether she has received a report from the examining authority in relation to the proposed Norwich to Tilbury Great Grid Upgrade.

Answer

Answered by Michael Shanks (Labour)

The Planning Inspectorate’s Report on the application for development consent for the Norwich to Tilbury project was received on the 10th November 2026.The statutory deadline for taking the decision is three months from this date, being the 10th February 2027.

How we got there

Question itemCoverageSpecificityRationale
Has the Secretary of State received the report from the examining authority on the proposed Norwich to Tilbury Great Grid Upgrade? Addressed Direct The question asks whether the Secretary of State has received the examining authority's report, and statement 1 directly confirms that the Planning Inspectorate's report was received on 10 November 2026, with statement 2 adding the decision deadline.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.