Asked by Tim Farron Liberal Democrat to Department for Environment, Food and Rural Affairs on 21 October 2026 — tabled under the Andy Burnham government

60/100 AMBER (60/100)

The reply gives a clear timetable for the reservoir: it has passed RAPID Gate 3 and a planning application is expected later in 2026. It also directly explains that Defra supports delivery through programme coordination and by resolving delivery issues. It does not answer the question of how the reservoir is prioritised relative to the Fens and Lincolnshire reservoirs, offering only a general statement that it remains a government priority, so the asker would likely need to follow up on that point.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, what the timetable is for the White Horse Reservoir (formerly the South East Strategic Reservoir Option) to move from pre-application to a submitted application; what role her Department has played in progressing it; and whether it will be treated as a priority alongside the Fens and Lincolnshire reservoirs.

Answer

Answered by Emma Hardy (Labour)

White Horse Reservoir would provide up to 271 million litres of water per day, strengthening water security across the South-East. It passed RAPID Gate 3 and is preparing a planning application expected later in 2026. Defra supports delivery through programme coordination and resolving delivery issues. It remains a government priority.

How we got there

Question itemCoverageSpecificityRationale
What the timetable is for the White Horse Reservoir (formerly the South East Strategic Reservoir Option) to move from pre-application to a submitted application Addressed Direct The reply gives a concrete progress marker (passed RAPID Gate 3) and a date for the next stage (a planning application expected later in 2026), which together indicate the timetable from pre-application to submission.
What role the Department has played in progressing the White Horse Reservoir Addressed Direct The statement that Defra supports delivery through programme coordination and resolving delivery issues directly describes the Department's role in progressing the reservoir.
Whether the White Horse Reservoir will be treated as a priority alongside the Fens and Lincolnshire reservoirs Partially Addressed Hedged The statement that the reservoir 'remains a government priority' gives a general affirmation but does not address how it is prioritised relative to the Fens and Lincolnshire reservoirs.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.