Question
The reply does not provide the regular updates on spending and contract milestones that was asked for, and it gives no reason for declining. It also says nothing about technical performance. Instead, it offers an independent evaluation with findings published at key points, including during delivery. That partly addresses the underlying concern about transparency, but a member of the public would likely need to ask again for the regular updates and performance information.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Business, Innovation, Science and Trade, with reference to the Department’s press release entitled World-first mission puts UK expertise to work to help clean up space, published on 15 October 2026, whether the Department plans to publish regular updates on the mission’s expenditure, progress against contractual milestones and technical performance before the planned launch in 2029.
Answer
The UK ADR contract is expected to sustain 20-25 UK jobs with 10-15 jobs created at ClearSpace UK. The UK Space Agency does not intend to publish regular updates on mission expenditure and progress against contractual milestones. However, we are planning an independent evaluation of the mission as part of wider monitoring and evaluation of its In-Orbit Servicing, Assembly and Manufacturing programmes. This will look at how the mission is being delivered, the outcomes it achieves and the benefits it delivers relative to its costs. We intend to publish evaluation findings at key points, including during delivery, in line with government standards on publishing research and analysis. Suppliers with a UK footprint represent 55% of ClearSpace’s supply chain, which represents 70% of contract spend.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| Whether the Department plans to publish regular updates on the mission's expenditure, progress against contractual milestones and technical performance before the planned launch in 2029. | Partially Addressed | Direct | The reply directly declines to publish regular updates on expenditure and contractual milestones (seq 2) with no stated reason, and does not address technical performance at all. It substitutes a concrete commitment to an independent evaluation with findings published at key points, including during delivery (seqs 3-5), which partly answers the underlying transparency concern but is not the regular updates asked for. |