The reply gives a specific date for the September 2026 formal review and a concrete date for the next scheduled NADG deep dive. It does not say when the review the question actually asked about will be completed, and the date it does give falls outside the 2026 period the question covered. A member of the public would likely need to ask again for the completion date of the specific review they asked about.
Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Defence, pursuant to the answer of 8 September 2026 to question 23361 on Defence, by when in 2026 he plans to have completed the formal review into the Next Generation (Fixed) Communication Network.
Answer
Immediately following the March 2026 Gateway Review, the Next Generation (Fixed) Communication Network (NGCN) programme developed an Assurance Action Plan (AAP) and began working to close the recommendations and associated actions. A formal review of the AAP was subsequently held 14-18 September 2026. Following that review, the NGCN Programme is continuing to work closely with National Armaments Plans & Portfolios (NA-P&P) to close out the remaining actions, and we anticipate the next formal review will be a National Armaments Director Group deep dive in Q1 Financial Year 2027-28.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| By when in 2026 the Secretary of State plans to complete the formal review into the Next Generation (Fixed) Communication Network | Partially Addressed | Direct | Statement 4 gives a concrete date for the next formal review (a NADG deep dive in Q1 FY2027-28), and statement 2 records the September 2026 formal review. However, the reply does not say when the review the item names will be completed, and the date it gives falls outside the 2026 period the question asked about. |