Question
The reply clearly answers the total spend question (£87.5 million to September 2026), and gives specific figures for land (£3.1 million) and advanced construction and preparatory works (£7.5 million). Design, planning and consent, and procurement costs are only included within a combined £72.4 million development figure, so the spend on each of these is not separately stated. A member of the public would likely need to ask for a breakdown of that development category to get the full picture.
Scored 13 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask His Majesty's Government how much funding has been spent on the A46 Newark bypass scheme to date, broken down by (1) design, (2) planning and development consent, (3) procurement, (4) land acquisition, and (5) other preparatory works.
Answer
As of September 2026, National Highways has spent £87.5 million on the A46 Newark Bypass scheme. National Highways records expenditure against established project cost categories. This comprises of £4.5 million on options, £72.4 million on development, including design, consenting and procurement, £3.1 million on land and £7.5 million on advanced construction and preparatory works.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| How much funding has been spent on the A46 Newark bypass scheme to date, in total. | Addressed | Direct | Statement 1 gives a total spend figure of £87.5 million to September 2026, which directly answers the request for total funding spent to date. |
| How much funding has been spent to date on design for the A46 Newark bypass scheme. | Partially Addressed | Hedged | Design is only mentioned as part of the blended £72.4 million 'development' category, with no separate design figure given and no statement that design is not separately tracked. |
| How much funding has been spent to date on planning and development consent for the A46 Newark bypass scheme. | Partially Addressed | Hedged | Planning and consenting costs are included only within the combined £72.4 million development figure, so the specific spend on planning and development consent is not isolated. |
| How much funding has been spent to date on procurement for the A46 Newark bypass scheme. | Partially Addressed | Hedged | Procurement is named only as one element of the blended £72.4 million development figure, with no separate procurement spend stated. |
| How much funding has been spent to date on land acquisition for the A46 Newark bypass scheme. | Addressed | Direct | Statement 3 states that £3.1 million has been spent on land, which directly answers the land acquisition spend question. |
| How much funding has been spent to date on other preparatory works for the A46 Newark bypass scheme. | Addressed | Direct | Statement 3 gives £7.5 million on advanced construction and preparatory works, which directly corresponds to other preparatory works spending. |