The reply gives a clear, direct reason for the delay: the scheme is being reset to keep it affordable, deliverable and good value for money, and the missing timetable follows from that reset. On recent progress, it only describes the ongoing reset, framed as the scheme's own process, and points to a separate written answer about benefits rather than progress. The asker would likely need to follow up to get a firm timetable and specific details of what has been achieved.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Environment, Food and Rural Affairs, with reference to the response of 9 February 2026 to UIN 110069, for what reason the next stage of the River Thames Scheme has not taken place; and what recent progress she has made on that project.
Answer
The River Thames Scheme is currently undertaking a reset to ensure it remains affordable, deliverable and provides value for money. For this reason, a timetable is not available for the project. I refer the hon. Member to the response given on 15 June 2026 to PQ UIN 9703 for details on the benefits.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What is the reason the next stage of the River Thames Scheme has not taken place? | Addressed | Direct | The reply gives a concrete reason for the delay: the scheme is undergoing a reset to ensure it stays affordable, deliverable and offers value for money, and the missing timetable follows from that reset. |
| What recent progress has the Secretary of State made on the River Thames Scheme? | Partially Addressed | Hedged | The ongoing reset is the only recent activity described, but it is framed as the scheme's own process rather than the Secretary of State's progress, and the referral to a PQ reply covers benefits rather than progress, so the item is only partly answered. |