Question
The question asked whether the Department would have to pay for early-stage work on the site even if it is later not used to accommodate asylum seekers. The reply answers this directly: the Department is contractually required to pay Kier for properly undertaken Stage 1 work, and that payment does not depend on the site later accommodating asylum seekers. It also states that if the site is found unviable, costs are limited to work properly incurred, so the answer is clear and committed on every point asked.
Scored 28 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for the Home Department, pursuant to the answer of 24 November 2026 to UIN 44632, whether her Department is liable to pay Kier for work relating to RAF Barnham regardless of whether the site is used to accommodate people.
Answer
The Department is contractually required to pay Kier Construction Limited for work properly undertaken under the Stage 1 (Design) contract for RAF Barnham. This covers specified design, survey and enabling works and is not conditional on the site subsequently being used to accommodate people seeking asylum. The Department has not committed to progressing to Stage 2 (Construction). Should the site be determined not to be viable during Stage 1, the Department would only be liable for costs properly incurred for work undertaken up to that point. No final decision has been made to use RAF Barnham to accommodate people seeking asylum. Further due diligence, assessments and approvals are required before any decision is taken on whether to proceed.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| Whether the Home Office is liable to pay Kier for work relating to RAF Barnham regardless of whether the site is used to accommodate people. | Addressed | Direct | The reply directly answers the liability question: the Department is contractually required to pay Kier for properly undertaken Stage 1 work, and this is expressly not conditional on the site later accommodating asylum seekers. Statement 4 adds the concrete fallback that costs are limited to work properly incurred if the site is found unviable. |