Asked by Dr Ben Spencer Conservative to Department for Business, Innovation, Science and Trade on 09 October 2026 — tabled under the Andy Burnham government

45/100 AMBER (45/100)

The reply gives firm timetables for both phases: Phase 1 is expected to be operational in 2028 and Phase 2 in financial year 2029-30. It is much vaguer on the other points. It gives no date for site selection, only that the process will start 'shortly', and no date for contract award, referring only to 'ongoing procurement processes'. It also does not name any sites or say which have submitted expressions of interest, so the asker would likely need to follow up on those points.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Business, Innovation, Science and Trade, what is the current timetable for (a) site selection, (b) contract award, (c) Phase 1 operation and (d) Phase 2 operation of the heterogeneous AI supercomputer; and which sites have submitted expressions of interest.

Answer

Answered by Kanishka Narayan (Labour)

We are progressing plans for a heterogeneous AI supercomputer to expand UK public AI compute capacity and introduce novel hardware supporting a range of AI workloads. Subject to ongoing procurement processes, Phase 1 is expected to be operational in 2028 and Phase 2 financial year 2029-30. An Expression of Interest for potential host sites launched in June 2026. The formal selection process will commence shortly. Further detail on grant or associated funding arrangements will be published when the formal competition opens. All potential applicants will receive information at the same time, ensuring the integrity of the competition process.

How we got there

Question itemCoverageSpecificityRationale
What is the current timetable for site selection for the heterogeneous AI supercomputer? Partially Addressed Hedged The reply gives no date for site selection; it only says the formal selection process will commence 'shortly' and that the host-site Expression of Interest launched in June 2026, which is related but not a timetable.
What is the current timetable for contract award for the heterogeneous AI supercomputer? Partially Addressed Hedged The reply refers only to 'ongoing procurement processes' without giving any date or timing for contract award.
What is the current timetable for Phase 1 operation of the heterogeneous AI supercomputer? Addressed Direct The reply states that Phase 1 is expected to be operational in 2028, which directly gives the requested timetable.
What is the current timetable for Phase 2 operation of the heterogeneous AI supercomputer? Addressed Direct The reply states that Phase 2 is expected in financial year 2029-30, which directly gives the requested timetable.
Which sites have submitted expressions of interest for the heterogeneous AI supercomputer? Not Addressed Generic The reply gives only the launch date of the Expression of Interest and does not name any sites or say which have submitted expressions of interest.