Question

Asked by Dame Chi Onwurah Labour to Department for Energy Security and Net Zero on 18 November 2026 — tabled under the Andy Burnham government

28/100 AMBER (28/100)

The reply touches on the question only in general terms. It says that managing speculative data centre demand supports the UK's competitiveness as an investment location, and it describes current investment delays. It does not assess how the Commitment Fee compares with arrangements in other countries, and it defers the fee's design to Ofgem. The reply is therefore mostly hedged, and the person who asked would likely need to ask again for a specific assessment.

Scored 27 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, what assessment she has made of the potential impact of Ofgem’s proposed Data Centre Commitment Fee on the UK’s competitiveness as a destination for data centre investment relative to other countries.

Answer

Answered by Michael Shanks (Labour)

Significant investments in UK data centres, as well as other demand projects of strategic national importance, continue to be delayed by the high volume of speculative data centre projects in the queue for demand side grid connections. Government strongly supports measures to manage speculation and oversubscription of data centres, ensure that scarce capacity is held by credible, deliverable projects, and ultimately maintain the UK's competitiveness as a location for investment. The design of the proposed Data Centre Commitment Fee is a matter for Ofgem, and its decision will be published in due course.

How we got there

Question itemCoverageSpecificityRationale
What is the department's assessment or view of the potential impact of Ofgem's proposed Data Centre Commitment Fee on the UK's competitiveness as a destination for data centre investment relative to other countries? Partially Addressed Hedged Statement 2 states the department's general view that measures to manage speculative data centre demand support UK competitiveness as an investment location, and statement 1 describes current investment delays. However, neither gives an assessment of the Commitment Fee's impact relative to other countries, and statement 3 defers the fee's design to Ofgem, so the reply is only a general position rather than the specific assessment asked for.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.