Asked by Munira Wilson Liberal Democrat to Department for Education on 09 October 2026 — tabled under the Andy Burnham government

80/100 GREEN (80/100)

The reply gives specific, direct information on progress at Enterprise Academy. It confirms a Technical Adviser has been appointed, the design is being reviewed against current specifications, surveys are under way, and the project team is engaging with the trust and local authority. It anticipates buildings being ready for September 2029, but the opening date itself is to be agreed later, so that remains open.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Education, what progress has been made on the delivery of Enterprise Academy, the proposed new Autism Spectrum Disorder Free School in Malvern, Worcestershire, following the letter sent by Worcestershire County Council on the 13th August 2026.

Answer

Answered by Josh MacAlister (Labour)

Following the government's announcement of a £3 billion investment for additional special educational needs and disabilities (SEND) places, the department remains committed to supporting children and young people with SEND and to delivering Enterprise Academy. The department has appointed a Technical Adviser to develop the feasibility study for Enterprise Academy. As part of this work, the design is currently being reviewed to align with our latest school specifications and surveys are underway. The project team are engaging with MacIntyre Academies Trust and the local authority in relation to the new school. The feasibility study will determine the delivery programme. At present, the new school buildings are anticipated to be ready for September 2029. A provisional opening date will be agreed once there is sufficient confidence that the buildings can be completed on time, typically around 12 months before opening.
10% vibes

How we got there

Question itemCoverageSpecificityRationale
What progress has been made on the delivery of Enterprise Academy, the proposed new Autism Spectrum Disorder Free School in Malvern, Worcestershire. Addressed Direct The reply sets out concrete progress on Enterprise Academy: a Technical Adviser has been appointed, the design is being reviewed against current specifications, surveys are underway, the project team is engaging with the trust and local authority, and buildings are anticipated for September 2029, with the opening date to be agreed later.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.