Asked by Alison Griffiths Conservative to Department for Transport on 13 October 2026 — tabled under the Andy Burnham government

70/100 AMBER (70/100) DATA NOT HELD

The reply clearly explains the method used to put a value on delay, including incident-related delay, and cites the specific Department for Transport guidance it relies on. On the cost of incident-specific delay, it plainly states that neither the Department nor National Highways has produced assured estimates, which is an honest answer in its own right. It points to an all-causes annual estimate without stating the figure, and says updated estimates are in development, so a member of the public may still need to ask for the actual numbers.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Transport, pursuant to the Answer of 17 July 2026 to Question 18158 on Road Traffic, what methodology her Department uses to monetise delays caused by incidents on the strategic road network; and what estimate it has made of the total economic cost of such delays in the latest year for which data is available.

Answer

Answered by Justin Madders (Labour)

The Department provides values of travel time, which can be used to monetise costs of delay, including delay due to incidents. The methodology is set out in DfT’s Transport Analysis Guidance (TAG): https://www.gov.uk/guidance/transport-analysis-guidance , specifically TAG Unit A1.3 and the TAG data book. Neither the Department for Transport nor National Highways has produced assured estimates of total hours, or cost, of delay specifically attributable to incidents. An estimate of the economic cost per year of delay on the strategic road network, for all causes of delay, can be found at: https://nationalhighways.co.uk/media/nixpb1ed/managing-delay-on-the-strategic-road-network.pdf . National Highways is in the process of developing updated, suitable estimates, and more broadly continues to improve the data and understanding of delay across the strategic road network and publishes information in this area.

How we got there

Question itemCoverageSpecificityRationale
What methodology the Department uses to monetise delays caused by incidents on the strategic road network Addressed Direct The reply names the methodology: DfT travel-time values used to monetise delay, including incident delay, with the specific source given as TAG Unit A1.3 and the TAG data book.
What estimate the Department has made of the total economic cost of such delays in the latest year for which data is available Data Not Held Hedged The reply honestly states that neither DfT nor National Highways has produced assured estimates of the cost of incident-specific delay, which answers the incident-specific part. It substitutes an all-causes annual estimate, but only as a link without stating the figure, and notes that updated estimates are in development.