Question
The reply gives a clear figure for the number of publicly open, LEVI-funded chargers that are operational (1,268). It does not give the number of chargers installed but still awaiting grid connection, and it does not address that category at all. On chargers allocated under signed contracts, it declines to release figures, citing commercial sensitivity, so the asker would likely need to follow up for those numbers.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Transport, since 27 May 2026, how many of the charge points allocated through the Local EV Infrastructure Fund are (a) operational and open to the public, (b) installed but awaiting grid connection and (c) allocated but not yet installed.
Answer
As of 1 July 2026, 1,268 public chargers delivered through the Local EV Infrastructure Fund were operational and open to the public. Figures on the number of chargers committed through signed contracts are commercially sensitive, but the programme remains on track to deliver over 100,000 chargers.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| How many charge points allocated through the Local EV Infrastructure Fund since 27 May 2026 are operational and open to the public? | Addressed | Direct | The reply gives a specific figure of 1,268 LEVI-funded public chargers that are operational and open to the public, which is the requested count. It uses "delivered" rather than "allocated since 27 May 2026" and does not mention that cut-off date, so the framing is slightly different. |
| How many charge points allocated through the Local EV Infrastructure Fund since 27 May 2026 are installed but awaiting grid connection? | Not Addressed | Generic | No statement gives or addresses the number of chargers installed but awaiting grid connection. The only related statement refuses to release figures on chargers committed through signed contracts, which is a different category. |
| How many charge points allocated through the Local EV Infrastructure Fund since 27 May 2026 are allocated but not yet installed? | Partially Addressed | Hedged | The refusal on figures for chargers committed through signed contracts, citing commercial sensitivity, is the closest engagement with "allocated" chargers, but it gives no number for allocated-but-not-installed chargers. The stated reason is commercial sensitivity, so the item is only partly answered. |