Question

Asked by Priti Patel Conservative to Department for Transport on 19 October 2026 — tabled under the Andy Burnham government

45/100 AMBER (45/100)

The reply confirms that the Department intends to revoke the Order and names the statutory process it will use, so the core of the question is answered directly. It does not say when the revocation will happen, only that timing depends on completing that process. A member of the public would likely need to ask again for a date or an expected timescale.

Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Transport, when the Development Consent Order for the A12 Widening Scheme will be revoked.

Answer

Answered by Justin Madders (Labour)

The Department intends to take forward the statutory process for revoking the Development Consent Order. The timing of any revocation will be subject to completion of that process.

How we got there

Question itemCoverageSpecificityRationale
When the Development Consent Order for the A12 Widening Scheme will be revoked. Partially Addressed Direct The reply clearly confirms the Department intends to revoke the Order through the statutory process, which is a concrete mechanism, but it gives no date or indication of when revocation will occur, saying only that timing depends on completing that process.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.