Question
The reply does not give the capacity figures that were asked for. It declines to publish grid connection offers and site-level capacity, citing commercial sensitivity, and says three of five zones have consents and construction underway, but it gives no megawatt totals for consented, under-construction, or operational capacity. It does not address how much capacity pre-dates each zone's designation at all. Because the answer is mostly hedged and omits the key figures, the person who asked would likely need to submit a follow-up for specifics.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Business, Innovation, Science and Trade, for each designated AI Growth Zone, what capacity in megawatts (a) has a firm grid connection offer with a date, (b) has planning consent, (c) is under construction and (d) is operational as at the latest date for which figures are available; and how much of that capacity pre-dates designation.
Answer
AIGZ sites must be capable of delivering at least 500 MW of power for AI workloads by 2030, offer at least 100 acres of land by 2028, and demonstrate credible plans for delivery and local benefit, amongst other key criteria. Specific grid connection offers and site-level capacity figures are commercially sensitive and are not published by government. Of the five announced AI Growth Zones, three have relevant planning consents in place with construction underway. We are working to bring the remaining sites to the same position by the end of the year. New AI compute is expected to come online from 2027.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| For each designated AI Growth Zone, what capacity in megawatts has a firm grid connection offer with a date, as at the latest date for which figures are available? | Addressed | Direct | The reply declines to publish grid connection offers and site-level capacity figures, giving the reason that they are commercially sensitive, which is a direct, reasoned answer to the request for figures, though no MW figures are supplied. |
| For each designated AI Growth Zone, what capacity in megawatts has planning consent, as at the latest date for which figures are available? | Partially Addressed | Hedged | The reply says three of five zones have relevant planning consents and construction underway, but gives no MW figures for consented capacity, and the only other reference is the refusal to publish site-level capacity figures. |
| For each designated AI Growth Zone, what capacity in megawatts is under construction, as at the latest date for which figures are available? | Partially Addressed | Hedged | The statement that three zones have construction underway is a count of zones, not the MW under construction, and the refusal to publish site-level capacity figures is the only other relevant content. |
| For each designated AI Growth Zone, what capacity in megawatts is operational, as at the latest date for which figures are available? | Partially Addressed | Hedged | No operational MW figure is given for any zone; the refusal on site-level capacity is the only relevant statement, and the forward-looking remark that new compute is expected from 2027 does not describe current operational capacity. |
| For each designated AI Growth Zone, how much of the capacity identified pre-dates the zone's designation? | Not Addressed | Generic | Nothing in the reply addresses how much of the capacity pre-dates each zone's designation; the general refusal to publish site-level figures does not engage with this breakdown. |