Asked by Greg Smith Conservative to Department for Transport on 28 October 2026 — tabled under the Andy Burnham government

70/100 AMBER (70/100)

The reply gives a clear and specific completion date: the full scheme is forecast to open to traffic in financial year 2035-36, with some sections opening earlier. It does not give the estimated total cost, citing commercial sensitivities linked to future procurement. The asker therefore has the timescale they wanted but not the cost figure, so they may need to ask again for the cost.

Scored 14 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Transport, what estimate she has made of the cost of the A66 Northern Trans-Pennine dualling scheme; and in which financial year she expects the scheme to be completed.

Answer

Answered by Justin Madders (Labour)

The estimated total cost of the A66 Northern Trans-Pennine project cannot be disclosed at this stage due to commercial sensitivities associated with future procurement activity. The project is being delivered through a nine-year construction programme, with main construction commencing in November 2026. The full scheme is currently forecast to open to traffic in financial year 2035-36, with some sections expected to open earlier as construction is completed in phases.

How we got there

Question itemCoverageSpecificityRationale
What estimate the Secretary of State has made of the cost of the A66 Northern Trans-Pennine dualling scheme. Addressed Direct The reply directly declines to give the estimated total cost and states a reason (commercial sensitivities linked to future procurement), which is a complete answer under the convention for refusals with a stated reason.
In which financial year the Secretary of State expects the A66 Northern Trans-Pennine dualling scheme to be completed. Addressed Direct The reply gives a specific financial year, 2035-36, for when the full scheme is forecast to open to traffic, which answers the completion-year question, with a note that some sections open earlier.