Question

Asked by Alison Griffiths Conservative to Department for Environment, Food and Rural Affairs on 04 November 2026 — tabled under the Andy Burnham government

65/100 AMBER (65/100)

The reply gives a clear, direct answer on how the works are classified: as capital maintenance, with a 100% Grant in Aid rate. It also clearly states that the project was submitted before 2026 under the previous funding policy, not the April 2026 policy. However, the reply is hedged on the third point, saying only that eligibility and approval will be considered through the appraisal process as the project progresses, with no expected date or timing for that decision. A member of the public would have specific answers on two of the three points but would likely need to ask again about timing.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, how proposed works at Felpham Pumping Station are classified under the Environment Agency’s capital grant eligible investment guidance; whether the project has been submitted for consideration under the flood and coastal erosion risk management funding policy introduced in April 2026; and when the next funding or approval decision is expected.

Answer

Answered by Emma Hardy (Labour)

The project would attract 100% Grant in Aid funding as it is capital maintenance. It was submitted before 2026 under the previous funding policy.  Further funding eligibility and approval requirements will be considered through the appraisal process as the project progresses and future investment decisions are made.

How we got there

Question itemCoverageSpecificityRationale
How the proposed works at Felpham Pumping Station are classified under the Environment Agency's capital grant eligible investment guidance. Addressed Direct The reply classifies the works as capital maintenance and states the resulting 100% Grant in Aid rate, which answers how the works are classed under the capital grant guidance, although it does not name the guidance itself.
Whether the Felpham Pumping Station project has been submitted for consideration under the flood and coastal erosion risk management funding policy introduced in April 2026. Addressed Direct The reply states the project was submitted before 2026 under the previous funding policy, which directly answers whether it was submitted under the April 2026 policy.
When the next funding or approval decision on the Felpham Pumping Station project is expected. Partially Addressed Hedged The reply only says eligibility and approval will be considered through the appraisal process as the project progresses, giving no expected date or timing for the next funding or approval decision.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.