The reply clearly explains that the estimates were assured within HS2 Ltd and then independently reviewed by the Department, including by its Economic Centre of Excellence and independent project advisers. It does not say whether an external body such as the National Audit Office audited the estimates, so that part of the question is only partly answered and the reply relies on advisers rather than a formal external audit. A member of the public would have a clear answer on the review process but may need to ask a follow-up about external audit.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Transport, what (a) independent assurance, (b) external audit and (c) third-party review was conducted on the (i) cancellation and (ii) remediation cost estimates contained in, or used to inform, the document entitled High Speed 2 (HS2) Phase 1: decision to continue delivery following programme reset – Accounting Officer Assessment summary (May 2026), updated on 19 May 2026.
Answer
The cancellation and remediation cost estimate assumptions were initially assured within HS2 Ltd. The analysis was then reviewed and assured by the Department of Transport, including the Department’s independent project advisors. As part of the Accounting Officer Assessment process, the analysis was independently reviewed by the Department’s Economic Centre of Excellence. The HS2 reset has, and continues to receive, Parliamentary scrutiny.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What independent assurance was conducted on the cancellation and remediation cost estimates contained in, or used to inform, the High Speed 2 (HS2) Phase 1: decision to continue delivery following programme reset – Accounting Officer Assessment summary (May 2026), updated on 19 May 2026? | Addressed | Direct | Statement 3 names an independent review by the Department's Economic Centre of Excellence and statement 2 names assurance by the Department including its independent project advisors, which together describe independent assurance of the estimates; statement 1 adds that assumptions were first assured within HS2 Ltd. |
| What external audit was conducted on the cancellation and remediation cost estimates contained in, or used to inform, the High Speed 2 (HS2) Phase 1: decision to continue delivery following programme reset – Accounting Officer Assessment summary (May 2026), updated on 19 May 2026? | Partially Addressed | Hedged | No statement mentions an external audit (such as by the National Audit Office or another external auditor); the nearest reference is to the Department's independent project advisors, who are external advisers but are not described as having audited the estimates. |
| What third-party review was conducted on the cancellation and remediation cost estimates contained in, or used to inform, the High Speed 2 (HS2) Phase 1: decision to continue delivery following programme reset – Accounting Officer Assessment summary (May 2026), updated on 19 May 2026? | Addressed | Direct | Statement 2 identifies the Department's independent project advisors as reviewing and assuring the analysis, which is a third-party review, and statement 3 describes an independent review by the Economic Centre of Excellence. |