Asked by Ben Obese-Jecty Conservative to Ministry of Defence on 12 October 2026 — tabled under the Andy Burnham government

85/100 GREEN (85/100)

The reply gives a specific, committed dry-dock timing for each of the three named lighthouses: Hurst Point in Q3 2027, Hartland Point in Q3 2026, and Anvil Point in Q2 2027. It also sets out the phasing and timing conditions that frame those dates. One weakness is that the Hartland Point timing is worded as if already completed rather than as a forward plan, so its status is slightly unclear. Overall, a member of the public would have clear dates to rely on for all three questions.

Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Defence, what the planned schedule is for the refit of Point-class vessels a) Hurst Point, b) Hartland Point and c) Anvil Point under the Strategic Sealift Interim contract.

Answer

Answered by Luke Pollard (Labour (Co-op))

All 4 Point-class vessels are scheduled an extensive refit under the Strategic Sealift Interim contract. The planned schedule for RoRo refits are phased to maintain the strategic sealift capability required to support Defence operations. Timings remain subject to operational requirements, shipyard availability and the condition of each vessel when work begins. Hurst Point is scheduled to dry dock in Q3 2027. Hartland Point dry docked this year, 2026 – in Q3. Anvil Point is scheduled to dry dock in Q2 2027. Eddystone dry docked this year, 2026 – in Q2.

How we got there

Question itemCoverageSpecificityRationale
What is the planned schedule for the refit of Hurst Point under the Strategic Sealift Interim contract? Addressed Direct Statement 4 gives a concrete planned timing for Hurst Point (dry dock in Q3 2027), and the phasing and timing caveats in statements 2 and 3 frame that schedule.
What is the planned schedule for the refit of Hartland Point under the Strategic Sealift Interim contract? Addressed Direct Statement 5 gives a specific dry-dock timing for Hartland Point (Q3 2026), though it is phrased in the past tense as if already completed rather than as a forward plan, which slightly weakens it as a 'planned' schedule.
What is the planned schedule for the refit of Anvil Point under the Strategic Sealift Interim contract? Addressed Direct Statement 6 gives a concrete planned timing for Anvil Point (dry dock in Q2 2027), with statements 2 and 3 providing the phasing and conditions context.