The reply explains that reusing plutonium was considered alongside immobilisation and gives reasons for not preferring it, including the lack of UK fast reactor projects, a uranium-only fleet, and greater delivery certainty for immobilisation. It does not address the recent developments in metallic fast reactor or uranium-transuranic fuel technologies that the question specifically asked about. The answer is therefore only partly responsive and largely hedged, and the person who asked would likely need to follow up for specifics on those technologies.

Scored 17 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, with reference to the Written Statement of 24 January 2025 on the Plutonium Disposition Strategy, what consideration was given in the decision to rapid developments in metallic fast-reactor fuel and uranium-transuranic fuel technologies that could utilise UK plutonium.

Answer

Answered by Michael Shanks (Labour)

The Department and the Nuclear Decommissioning Authority (NDA) considered both immobilisation and re-use options. There are no existing or planned fast reactor projects in the UK that could utilise the plutonium. All current and planned UK reactors use uranium fuel. Immobilisation can be delivered sooner and with greater certainty than re-use in fast reactors, due in part to removing reliance on delivery of a new reactor programme. Indefinite storage of plutonium is not an acceptable solution due to the high cost of management and the enduring safety and security burden.

How we got there

Question itemCoverageSpecificityRationale
What consideration was given, in the decision set out in the Written Statement of 24 January 2025 on the Plutonium Disposition Strategy, to rapid developments in metallic fast-reactor fuel and uranium-transuranic fuel technologies that could utilise UK plutonium. Partially Addressed Hedged The reply confirms that re-use was considered alongside immobilisation and gives reasons it was not preferred (no UK fast reactor projects, uranium-only fleet, greater delivery certainty for immobilisation), but it never addresses the rapid developments in metallic fast-reactor or uranium-transuranic fuel technologies that the question specifically asks about.