The reply gives a specific, committed figure for each of the three time thresholds asked about. It reports 56 eligible Building Safety Fund buildings where remediation started more than one year earlier and has not reached practical completion, 41 where it began more than two years earlier, and 7 where it began more than five years earlier. A member of the public would have the concrete numbers they asked for and would not need to resubmit the question.

Scored 17 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Housing, Communities and Local Government, how many remediation works on residential buildings funded through the Government's Building Safety Fund have been ongoing for longer than i) one year, ii) two years or iii) five years.

Answer

Answered by Florence Eshalomi (Labour (Co-op))

As of 27 August 2026, there were 56 eligible Building Safety Fund buildings where remediation works had started more than one year earlier and had not yet reached practical completion. Of these, 41 buildings had started remediation more than two years earlier, including 7 buildings where remediation had begun more than five years earlier.

How we got there

Question itemCoverageSpecificityRationale
How many remediation works on residential buildings funded through the Building Safety Fund have been ongoing for longer than one year? Addressed Direct Statement 1 gives a specific figure of 56 eligible Building Safety Fund buildings where remediation started more than one year earlier and has not reached practical completion, which directly answers the one-year item.
How many remediation works on residential buildings funded through the Building Safety Fund have been ongoing for longer than two years? Addressed Direct Statement 2 states that 41 buildings had remediation begun more than two years earlier, a concrete figure that directly answers the two-year item.
How many remediation works on residential buildings funded through the Building Safety Fund have been ongoing for longer than five years? Addressed Direct Statement 2 gives the figure of 7 buildings where remediation began more than five years earlier, directly answering the five-year item.