Question
The reply clearly answers two parts of the question: it confirms that formal Service Improvement Plan notices have been used, and it states that step-in and termination are being assessed as contractual options, with the stated conditions not yet met. It only partly answers whether a Rectification Plan notice has been issued for this specific contract, referring to past performance in general terms. The question about options available before 2030 gets a vague response, naming step-in and termination without setting out the exit routes or timeframe, so the person asking would likely need to follow up for specifics.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Justice, whether his Department has (a) issued Serco with a formal (i) remediation and (ii) performance improvement notice and (b) considered exercising any contractual (A) step-in and (B) termination rights in relation to the electronic monitoring contract; and what options exist to exit the contract before 2030.
Answer
The Department has used a range of contractual levers in response to previous performance concerns and issues, including formal Rectification Plan and Service Improvement Plan notices. These form part of the contractual mechanisms available to the Department to hold Serco to account. The Department continues to assess the contractual options available to it, including step-in and termination, as part of its contingency planning. These rights can only be exercised where the relevant contractual conditions and thresholds are satisfied. The conditions necessary to exercise these rights have not currently arisen. The Department continues to monitor performance and keeps the appropriate contractual response under review.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| Whether the Department has issued Serco with a formal remediation notice in relation to the electronic monitoring contract. | Partially Addressed | Direct | The reply says the Department has used Rectification Plan notices, which are the contractual equivalent of a remediation notice, but it refers to past performance concerns generally and does not confirm whether such a notice has been issued for this contract. |
| Whether the Department has issued Serco with a formal performance improvement notice in relation to the electronic monitoring contract. | Addressed | Direct | The reply explicitly names formal Service Improvement Plan notices as having been used and as part of the mechanisms for holding Serco to account, which answers whether a performance improvement notice has been issued. |
| Whether the Department has considered exercising any contractual step-in rights in relation to the electronic monitoring contract. | Addressed | Direct | The reply states that the Department continues to assess step-in as one of its contractual options, and adds that the conditions for exercising it have not yet arisen, which directly answers whether step-in has been considered. |
| Whether the Department has considered exercising any contractual termination rights in relation to the electronic monitoring contract. | Addressed | Direct | The reply explicitly names termination as an option under assessment in contingency planning, along with the threshold conditions and the statement that those conditions have not arisen, which directly answers whether termination rights have been considered. |
| What options exist for the Department to exit the electronic monitoring contract before 2030. | Partially Addressed | Hedged | The reply names step-in and termination as options being assessed, but it does not set out what exit routes exist or address the 2030 timeframe, so the answer about options before 2030 is vague. |