Question
The reply gives a specific answer on the power side of the question, naming a power supply upgrade between Euston and Bourne End with a cost of about £70 million and a completion date. It says little about other infrastructure, and it only partly answers the funding question: only the Euston to Bourne End upgrade is clearly funded, while other possible improvements are described as still under consideration. A member of the public would get a concrete starting point but would likely need to ask follow-up questions about the other improvements and their funding.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Transport, What assessment her Department has made of the infrastructure and power supply improvements needed to enable additional passenger services on the West Coast Main Line South while maintaining timetable resilience; and which of those improvements have funding allocated.
Answer
Works have started on an approximately £70 million power supply upgrade between Euston and Bourne End, which will greatly reduce delays caused by power trips and outages. I expect this to be complete in early 2028. The Department recognises that power supply upgrades are essential to support additional passenger services and timetable resilience and is actively considering further interventions as part of a coordinated power supply strategy for the West Coast South route.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What is the Department's assessment or view of the infrastructure and power supply improvements needed to enable additional passenger services on the West Coast Main Line South while maintaining timetable resilience? | Addressed | Direct | The reply gives a concrete assessment: a named power supply upgrade (about £70 million, Euston to Bourne End) with a stated benefit and completion date, plus an acknowledgement that power upgrades are essential for additional services and timetable resilience, and a commitment to consider further interventions. It covers the power side of the question but says little about non-power infrastructure. |
| Which of those infrastructure and power supply improvements have funding allocated? | Partially Addressed | Direct | Only the Euston to Bourne End upgrade is identified as underway with a cost, which implies funding, but the reply never states funding allocations explicitly. The further interventions are described only as under consideration, so the reply leaves open which other improvements have funding. |