Question
The reply gives a clear, specific date for each project's main milestone. It states that current plans point to Fens benefits from 2036 and to Lincolnshire becoming operational in 2040, though both are subject to planning, regulatory approval and delivery. It does not give any start or completion dates for the examination and decision stages for either project, offering only general caveats about planning and approvals, so the person who asked would likely need to follow up for those timings.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Environment, Food and Rural Affairs, whether the Fens Reservoir is on course to be completed by 2036 and the Lincolnshire Reservoir to be operational by 2040; and what the latest projected dates are for the start and completion of examination and decision for each.
Answer
Fens and Lincolnshire reservoirs would increase water supply and strengthen drought resilience in eastern England. Current plans indicate benefits from Fens from 2036 and operation of Lincolnshire from 2040, although timings remain subject to planning, regulatory approvals and delivery.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| Whether the Fens Reservoir is on course to be completed by 2036 | Addressed | Direct | The reply states that current plans indicate Fens benefits from 2036, which answers the 2036 target, though it frames this as benefits rather than completion and caveats it as subject to planning and delivery. |
| Whether the Lincolnshire Reservoir is on course to be operational by 2040 | Addressed | Direct | The reply gives the 2040 operational date for Lincolnshire under current plans, with the same caveat that timings remain subject to planning, regulatory approvals and delivery. |
| What are the latest projected start and completion dates for the examination and decision for the Fens Reservoir | Not Addressed | Generic | The reply gives no start or completion dates for the Fens examination and decision stages; it only mentions in general terms that timings depend on planning and regulatory approvals. |
| What are the latest projected start and completion dates for the examination and decision for the Lincolnshire Reservoir | Not Addressed | Generic | The reply gives no start or completion dates for the Lincolnshire examination and decision stages; it only generically notes that timings depend on planning and regulatory approvals. |