The reply directly addresses the question about why the unproductive hours arose. It gives the relevant hours and cost figures for the period and states the reasons plainly: Government Furnished Assets were not available to the supply chain when required, and the contractual arrangements for coordinating their provision across industrial partners were still being refined. The explanation is specific rather than hedged, so a member of the public would likely understand the cause without needing to ask again.
Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Defence, pursuant to the answer of 23 September 2026 to question 22803 on Nuclear Submarines: Procurement, for what reason those hours were unproductive.
Answer
The Prime Contractor recorded 39,872 unproductive hours in 2025-26, a significant reduction from the 94,640 hours recorded in 2024-25. This equated to around 6% of the contract value in 2025-26. These hours arose where Government Furnished Assets (GFA) were not available to the supply chain when required, and where contractual arrangements for coordinating provision across multiple industrial partners were still being refined. Mitigating action has since been taken, including a recruitment pause and the adoption of agile courseware development, which has contributed to a significant reduction in losses in 2025-26 compared with previous years.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| For what reason were the hours referred to in the answer of 23 September 2026 to question 22803 on Nuclear Submarines: Procurement unproductive? | Addressed | Direct | The question asks why the unproductive hours arose, and statement 3 directly gives the reasons: Government Furnished Assets were not available to the supply chain when required, and contractual arrangements for coordinating provision across industrial partners were still being refined. Statements 1 and 2 supply the relevant hours and cost figures for the same period. |