Question
The reply gives concrete dates for when work is due to start at the sites in question, along with a general account of the approvals process. It does not say when the final surveys and approvals themselves will be completed, which was the core of the question. For the Woodvale item, the reply answers a different question, the date the works will finish, so it is not credited as an answer to what was asked. A member of the public would likely need to ask again for the specific completion date for surveys and approvals.
Scored 17 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Defence, pursuant to the answer of 16 September 2026 to question 28094 on Air Force: Military Bases, when final surveys and approvals will be completed in order to complete work on a) RAF Northolt, b) Leuchars and c) RAF Woodvale.
Answer
Projects within the Air Operational Support Programme transition through the Royal Institute of British Architecture approvals process, typically over a period of three to five years. Subject to these approvals, and balancing operational priorities, work at RAF Northolt is due to commence in Financial Year (FY) 2027/28, whilst work at Leuchars is scheduled for FY 2028/29. Work at RAF Woodvale is due to be completed by March 2027, subject to weather conditions.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| When will final surveys and approvals be completed to complete work at RAF Northolt? | Partially Addressed | Direct | The reply gives a concrete date (work to commence in FY 2027/28, subject to approvals) and a general three-to-five-year approvals timeline, but it never states when the final surveys and approvals themselves will be completed, substituting the start of works. |
| When will final surveys and approvals be completed to complete work at Leuchars? | Partially Addressed | Direct | The reply gives a concrete date for Leuchars work (FY 2028/29) and the general approvals process, but does not say when final surveys and approvals will be completed, so it answers a neighbouring question about works timing. |
| When will final surveys and approvals be completed to complete work at RAF Woodvale? | Partially Addressed | Direct MISREADS QUESTION | The reply gives a completion date for the Woodvale works (March 2027, subject to weather), which is a different milestone from when final surveys and approvals will be completed, and it does not say whether those approvals are already done. |