Question

Asked by Dr Ben Spencer Conservative to Department for Energy Security and Net Zero on 09 October 2026 — tabled under the Andy Burnham government

18/100 RED (18/100)

The reply is mostly hedged and does not give the committed figures the question asked for. It says a count of individual projects is not currently possible and gives no number of Gate 2 offers. It gives 72.8 GW of data-centre capacity, which is a different measure from the count of transmission-connected offers requested, and it gives no data-centre project count. On timing, it says connection dates extend to the late 2030s, which does not state the earliest date offered to a data centre under Gate 2 to Whole Queue and so does not answer that part of the question. The asker would likely need to follow up for specific figures and dates.

Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, how many transmission-connected demand projects have received Gate 2 offers under the Gate 2 to Whole Queue process; how many are data centres; and what the earliest and latest connection date is offered to a data centre.

Answer

Answered by Michael Shanks (Labour)

The National Energy System Operator (NESO) is currently implementing the Gate 2 to Whole Queue process and connection offers continue to be issued. Data collected in 2025 and published by NESO shows 72.8 GW of capacity allocated to data centres in the GB connection queue across transmission and distribution, with connection dates extending to the late 2030s. It is not currently possible to provide a count of individual projects. Government recently consulted on measures to manage the current oversubscription of data centre connections and will publish its response in due course.

How we got there

Question itemCoverageSpecificityRationale
How many transmission-connected demand projects have received Gate 2 offers under the Gate 2 to Whole Queue process? Partially Addressed Hedged The reply states that a count of individual projects is not currently possible, which is an honest gap, but it offers no count of Gate 2 offers and does not explain what has been issued under the process beyond noting that offers continue to be issued.
How many of the transmission-connected demand projects that have received Gate 2 offers under the Gate 2 to Whole Queue process are data centres? Partially Addressed Hedged MISREADS QUESTION The only figure given is 72.8 GW of data-centre capacity across transmission and distribution in the queue, which is a different dataset and metric from a count of transmission-connected Gate 2 offers, and no data-centre project count is provided.
What is the earliest connection date offered to a data centre under the Gate 2 to Whole Queue process? Not Addressed Generic The reply gives only that connection dates extend to the late 2030s, which describes the far end of the range and says nothing about the earliest date offered to a data centre under Gate 2 to Whole Queue.
What is the latest connection date offered to a data centre under the Gate 2 to Whole Queue process? Partially Addressed Hedged The statement that connection dates extend to the late 2030s gives an approximate latest date, but it is not specific to data centres or to the Gate 2 to Whole Queue offers and is not a precise date.