Question
The reply directly answers the question. It sets out the specific criteria for priority customers in a gas supply emergency: loss of gas that risks lives or would cause significant damage to major industrial sites, as assessed by gas transporters, and serious harm to human welfare, the environment or UK security that cannot reasonably be mitigated, as assessed by the Department for Energy Security and Net Zero. It also identifies the National Emergency Plan as the source and explains how priority customers are treated.
Scored 16 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 15 October 2026 to Question 33981, what criteria her Department uses to determine whether a gas consumer is classed as a critical customer for the purposes of gas load shedding during a national gas supply emergency.
Answer
As referenced in DESNZ’s National Emergency Plan for Downstream Gas and Electricity, priority customers have their supplies prioritised for as long as practicable during a Network Gas Supply Emergency. Priority customers include those where loss of gas could put lives at risk or cause significant damage to major industrial sites, as assessed by gas transporters; and those where loss of gas could cause serious harm to human welfare, the environment or UK security that cannot reasonably be mitigated, as assessed by DESNZ in consultation with relevant government departments. Domestic customers are disconnected as a last resort.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What criteria the Department uses to determine whether a gas consumer is classed as a critical customer for the purposes of gas load shedding during a national gas supply emergency. | Addressed | Direct | Statements 3 and 4 set out the concrete criteria for priority (critical) customers: loss of gas risking lives or causing significant damage to major industrial sites, assessed by gas transporters, and serious harm to human welfare, the environment or UK security that cannot reasonably be mitigated, assessed by DESNZ. Statement 1 points to the National Emergency Plan as the source, and statements 2 and 5 add how priority customers are treated. |