The reply sets out the national policy criteria for carbon capture applications, namely the Energy National Policy Statements EN-1 and EN-2. It describes concrete requirements, including the urgent-need policy, technically feasible capture plans, environmental effects assessment, and transport and storage arrangements. It does not single out privately developed projects, but the criteria apply to all such applications, so the question is covered, and a reader would likely have enough specific information to move on.

Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, on what criteria a decision is made about approving a Development Consent Order (DCO) for privately developed carbon capture projects.

Answer

Answered by Martin McCluskey (Labour)

The criteria for DCO decisions for all carbon capture projects are set out in the Energy National Policy Statements (EN-1: Energy, and EN-2: Natural Gas Electricity Generating Infrastructure). EN-1 establishes an urgent need for carbon capture and storage infrastructure as part of the energy mix and provides specific policy for the assessment of DCO applications. EN-2 sets out the assessment provisions that are applied to any gas fired power station with carbon capture. A project must demonstrate technically feasible plans for the carbon capture plant and assess its environmental effects, including the arrangements for the transport and storage of the captured carbon.

How we got there

Question itemCoverageSpecificityRationale
What criteria are applied when deciding whether to approve a Development Consent Order for privately developed carbon capture projects? Addressed Direct The reply names the governing criteria (EN-1 and EN-2 National Policy Statements), describes EN-1's urgent-need and assessment policy, and lists concrete requirements such as technically feasible capture plans, environmental effects assessment, and transport and storage arrangements. It does not single out privately developed projects, but the criteria it describes apply to all carbon capture DCO applications, which covers the item.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.