The reply directly answers the question about what the benefit-cost analysis showed, giving a specific figure of 4.89:1 from the March 2022 Outline Business Case. It also notes that the assessments have not been updated since the pause, which is useful context for how current that figure is. Because the answer is specific and committed, the asker would likely have what they need, though they may still want to ask whether the analysis will be refreshed.
Scored 15 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)
The question
To ask the Secretary of State for Transport, pursuant to the answer of 10 June 2026 to WPQ 7223, what the analysis of the benefit to cost ratio of the Ely Area Capacity Enhancement showed.
Answer
The March 2022 Outline Business Case for the Ely Area Capacity Enhancement scheme indicated a benefit cost ratio of 4.89 : 1. These assessments have not been updated since the scheme was paused by the previous Government in 2022. The Ely scheme remains under consideration and will be reviewed as future funding opportunities arise.
How we got there
| Question item | Coverage | Specificity | Rationale |
|---|---|---|---|
| What the analysis of the benefit to cost ratio of the Ely Area Capacity Enhancement showed. | Addressed | Direct | Statement 1 gives the specific result of the benefit-cost analysis (a ratio of 4.89:1 in the March 2022 Outline Business Case), which directly answers what the analysis showed. Statement 2 adds that the assessments have not been updated since the pause, which places the figure in context. |