Question

Asked by Graham Leadbitter Scottish National Party to Department for Energy Security and Net Zero on 10 November 2026 — tabled under the Andy Burnham government

30/100 AMBER (30/100)

The reply only partly answered the question. It explained that Ofgem makes the final decision, that the process includes locational factors, and that final decisions are expected later this year, but it did not say what the department itself is doing about the concentration of projects in north Scotland before those decisions. Because the answer was mostly hedged and pointed to a later decision, the questioner would likely need to ask again for specific commitments.

Scored 14 Nov 2026 — may change if this question is rescored under an updated model or prompt (see Methods)

The question

To ask the Secretary of State for Energy Security and Net Zero, what steps she is taking to address the geographical differences resulting from Scottish-based projects on Ofgem’s ‘minded-to’ list for Long Duration Energy Storage (LDES) support being located in the north of Scotland, prior to a final decision on which projects to support.

Answer

Answered by Michael Shanks (Labour)

Ofgem is the independent regulator and decision maker for implementation of the Long Duration Electricity Storage Cap and Floor scheme, appointed by government to deliver the policy. It assessed all eligible projects through its published Multi Criteria Assessment framework, which included consideration of locational factors. Ofgem has published its minded-to decisions and their rationale. It is reviewing responses to its consultation on the minded-to decisions and is aiming to confirm final decisions later this year.

How we got there

Question itemCoverageSpecificityRationale
What the department is doing to address the geographical differences resulting from Scottish-based projects on Ofgem's 'minded-to' list for Long Duration Energy Storage support being located in the north of Scotland, prior to a final decision on which projects to support. Partially Addressed Hedged The reply mainly refers the question to Ofgem as the decision maker and describes the process (Multi Criteria Assessment including locational factors, published minded-to decisions, consultation under review, final decisions expected later this year). It names a mechanism that touches on location, but never says what the department itself is doing to address the north Scotland concentration before the final decision, so the substance of the question is only partly answered.

Feedback on this grading

Think this verdict is wrong, or that the question and answer have been mismatched? Let us know.

Submitting this needs Google reCAPTCHA to block spam, which sets cookies from google.com on your device — see our Cookies policy for details. Accept these cookies to show the form.